The next step of migration is to re-upload EPTs to set necessary Project Plan Templates.
1. Open FluentBooks workspace with source PWA Configuration, start Upload configuration to PWA wizard.
2. In the Step 2 select only Enterprise Project Types and proceed with the upload process.
3. Create a test project from each EPT in the target PWA to verity that they work correctly. Once the test projects / sites are verified, delete them.
- If the target PWA is Project Server next step is to Upload Projects using 'Upload Projects from FPP files' wizard
- If the target PWA is Project Online proceed to the Update Project Site Creation Settings