Planner -> Monday.com migration supported entities

All information in this article also applies to the MS Planner -> Monday.com and Planner (basic plans) -> Monday.com migration scenario. 

Source System Entities

Supported

Target System Entities

Notes

Planner Plans 

+

Boards


 

Plan Buckets

+

Board Groups

 

Plan Tasks

+

Board Items

 

Task field values

+

Item column values

Please refer to the list of supported task fields below

Users

̶

Users

Users are not migrated but mapped with the target users. Necessary users should already exist in the target tenant.

Plan task user assignments

+

Item user assignments

Mapped users, assigned to tasks in the source Plan, will be added as members to the corresponding target Board and assigned to Board items

Microsoft 365 Groups

+

Workspaces

Target Workspaces can be created with the source Microsoft 365 group names only for the selected Plans 

Microsoft 365 Group Members

+

Board Members

All source group members (for the selected Plans) will be added to the target Board Members if the corresponding users exist in the target system and are mapped.

Microsoft 365 Group Owners

+

Board Owners

All source group owners (for the selected Plans) will be added to the target Board Owners if the corresponding users exist in the target system, have the Member or the Admin role and are mapped.

Microsoft 365 Group Privacy

̶

Workspace/Board Type

Workspaces will be created of the Open type, and Boards will be created of the Main (Public) type

 

Supported Task/Item Fields

Source Task Field

Supported

Target Item Field

Notes

Task Name

+

Item Title 

 

Bucket Name

+

Group Name

 

Assignments

+

Assignments 

(People type)

 

Start Date

+

Start Date 

(Date type)

 

Due Date

+

Due Date 

(Date type)

 

Progress (Percent Complete)

+

Progress
 (Status/Color type)

 

Priority

+

Priority

(Status/Color type)

 

Notes

+

Description

(Long Text type)/
 Updates

 

Attachments

+

Updates  

Source file and link attachments will be added to the item Updates section, in an update posted by the migration account. 

Checklist

+

Checklist in item Updates

Checklist will be added to the item Updates section, in an update posted by the migration account.

Labels

+

Labels

(Dropdown type)

 

Comments

+

Updates

Comments migration is supported

Created By

+

Created By
(People type)

Source task creator will be specified in the 'Created By’ item field, while the migration account will be set as the item creator in the default ‘Creation Log’ field.

Creation date & time

+

Created Date
(Date type)

Source task creation date & time will be specified in the ‘Created Date’ item field, while the date when an item was created during the migration would be set in the default ‘Creation Log’ field.

Completed By

+

Completed By
(People type)

 

Completed date & time

+

Completed Date
(Date type)

 

Last Changed By

̶

Last Updated

Target Monday.com migration account would be specified in that field for a new item or an existing item that was updated during the migration.

Last Changed time

̶

Last Updated

Last Updated time would be set to the time when the migration was performed, and an item was updated.


During the migration, the target item fields will be created in new Boards with the names and types specified in the task field mapping (‘Target Item Field’ column of the table). 

 