Project Migrator allows migrating data from Smartsheet to Planner Premium (Project for the web).
In this article, we will review the basic information about the Smartsheet -> Planner Premium scenario and the steps you need to take to successfully configure and run the migration process.
This migration scenario enables organizations to publish project plans from Smartsheet to Planner Premium so team members can work on assigned tasks, report progress, and updates.
There are four main steps you need to perform to launch the migration process:
Step1: Connect to source and target systems. On this step, you need to establish a connection between the source Smartsheet environment and the target Planner Premium environment.
Step 2: Select source data. Project Migrator allows selecting all data at once or only the needed items.
Step 3. Object mapping. Project Migrator provides a user-friendly, built-in data mapping interface, where you can review what data from the Smartsheet environment goes to which fields in the target Planner Premium environment.
Step 4: Launching the migration process.
All these steps are described in detail in the Smartsheet -> Planner Premium scenario migration steps article.
Also, please review the known limitations of the data migration article.