Exploring the Single-Page Templates

The Single-page template in Project Story presents a compact, easy-to-read summary of a plan on a single screen. It includes essential details and dynamically generated content to provide stakeholders with a clear snapshot of plan health and activity. 

This structured layout provides a focused overview of the plan, enabling stakeholders to quickly assess the current status, key issues, and next steps, making the Single-page Project Story Report ideal for quick executive summaries and concise reporting.

There are two types of multi-page reports: Colorful single-page template (for Project Accelerator) and Colorful single-page template (for OOB Planner Premium). The key difference lies in the data retrieved from Planner.

When using the Colorful single-page template (for Project Accelerator) report, a broader dataset is available, and more information is retrieved for reporting. This includes additional fields and entities that enable more detailed and comprehensive reports.

Below is a breakdown of what is included in this layout and how it is structured.


Colorful single-page template (for Project Accelerator)

At the top of the report, the following details are displayed: Plan Name, Plan Owner, Statuses, and the previous Week Ending date. 

Status Summary

This section provides an AI-generated narrative summary of the plan's current state. It is broken down into several paragraphs:

  • Project Status: A few sentences describing the overall status of the plan.
  • Plan Highlights: A paragraph summarizing the current state of: Milestones, Issues, Risks, Goals, Tasks, and Budget.

Focus Areas (Upcoming Activities)

This section highlights the most imminent tasks:

  • Displays up to 8 upcoming tasks where start date is today + 1 day or later
  • If no tasks meet the criteria, the message "There are no upcoming tasks" is shown
  • Tasks are sorted by ascending start date

Dates&Milestones

This table shows up to 5 upcoming milestones:

  • Only active milestones are included (completed ones are excluded)
  • Milestones are selected if they fall within ±15 days of today
  • Sorted by due date (descending)

Issues

  • Up to 5 active issues are displayed
  • Closed issues are excluded
  • Issues with due dates are listed first, followed by those without dates

Risks

  • Displays up to 5 top risks
  • Excludes closed risks
  • Risks with due dates are listed first, followed by those without


Colorful single-page template (for OOB Planner Premium)

At the top of the report, the following details are displayed: Plan Name, Plan Owner, Progress and Effort, and the previous Week Ending date. 

Status Summary

This section provides an AI-generated narrative summary of the plan's current state. It is broken down into several paragraphs:

  • Project Status: A few sentences describing the overall status of the plan.
  • Plan Highlights: A paragraph summarizing the current state of: Milestones, Issues, Risks, Goals, Tasks, and Budget.

Focus Areas (Upcoming Activities)

This section highlights the most imminent tasks:

  • Displays up to 8 upcoming tasks where start date is today + 1 day or later
  • If no tasks meet the criteria, the message "There are no upcoming tasks" is shown
  • Tasks are sorted by ascending start date

Dates&Milestones

This table shows up to 5 upcoming milestones:

  • Only active milestones are included (completed ones are excluded)
  • Milestones are selected if they fall within ±15 days of today
  • Sorted by due date (descending)

Risks

  • Displays up to 5 top risks
  • Excludes closed risks
  • Risks with due dates are listed first, followed by those without